2 min read
Power Management System delivered for Zero Cost Energy Future: Phase 2
Challenge SA Water provides clean water and removes, treats, and recycles wastewater for more than 1.7 million customers across South Australia....
CASE STUDY
Admin : Jun 11, 2019
3 min read
Utilities
25 remote communities powered by the sun. Each community’s Energy Management System provides the monitoring and control needed to deliver all 25 communities with a reliable, consistent solar-hybrid electricity supply.
Solar and battery control system integration, remote software updates, electrical system integration, switchboard manufacture, remote communications, energy storage and load
management systems.
Multiple locations, Northern Territory, Australia
Power and Water Corporation is responsible for electricity transmission and distribution, and provides water and sewerage services across the Northern Territory — an area with more than 1.3 million square kilometres and some of the most vastly distributed communities in the world.
As such, the utility must provide the bulk of power to these communities via remote power generation sites. These sites have, until recently, been powered through diesel generators that are costly to run, challenging to fuel and unsustainable.

Power and Water sought to transform the way these communities were powered by rolling out solar under the Northern Territory Solar Energy Transformation Program (Solar SETuP). The four-year ARENA program aimed to deliver two off-grid solar solution types for 25 remote communities:
Control system and automation experts SAGE Automation were engaged to deliver this critical component of the system. Having delivered and serviced more than 50 of Power and Water’s control systems since 2007, SAGE were able to deliver a maintainable and scalable solution to allow the rapid rollout of solar.
SAGE delivered the automation and control needed to transform 25 remote power stations into ‘solar-diesel hybrid’ power stations. This included delivering remote control, monitoring and load management capability of different generation assets such as solar, diesel and battery storage. A high degree of collaboration with the Power and Water team was critical to the project’s success.
The solar remote monitoring and control systems solution used: Schneider Modicon M340 PLC, Woodwood easYgen generator controllers, Schneider PowerLogic PM5560 power meters, Citect SCADA, OSIsoft PI historian, PLC, SMA cluster controller and satellite communication.

Power and Water have harnessed the Northern Territory’s biggest asset – immense land and sun availability, to provide its remote communities with a sustainable, natural power source.
Indigenous communities support the solar initiative that ‘generates energy from country’ and it will support remote communities well into the future.
Snapshot results:

Project: Nauiyu solar-battery
Aim: Replace daytime diesel generation with battery stored power to supplement intermittent solar supply. Diesel would come online at night.
Challenge: Technically, the control system would need to integrate with battery, diesel generators, and the power station and be able to shift between energy sources seamlessly
Solution: Advanced energy management control system including Software engineering, Design, Manufacture, Commissioning
Outcome: Power and Water achieved 50% of community power with solar and battery alone. The site runs on average 12 hours in “diesel-off mode” each day, typically 9 am to 9 pm. Reliability and monitoring are ensured with the remote control system and SCADA interface.
2 min read
Challenge SA Water provides clean water and removes, treats, and recycles wastewater for more than 1.7 million customers across South Australia....
1 min read
Challenge SA Water delivers clean water, removes and treats wastewater, and recycles wastewater for more than 1.7 million customers across South...
1 min read
Opportunity Snowy Hydro Limited is an Australian energy business, providing on-demand energy delivered by 15 power stations across New South...